By: P.T., STA
TEB, a Brestanica-based natural gas power station, has launched its seventh gas unit after its construction started in July 2019.
Together with unit six, PB7 will replace the first three gas units from 1974. As part of the trial launch the turbine was turned on on Friday after TEB completed in December cold tests AND obtained all the required certificates. PB7 is to start supplying power to the grid at the end of the month.